Week 13 Update
Last updated
Last updated
What was Accomplished:
made minor adjustments to syringe pump to account for mounting
CADed out mounting system
printed out ABS spin coater components, and checked if ABS components were flawed
Roadblocks: None
Plans for next week:
Print Syringe Mounting + mount on top of the actual assembly
Finalize assembling all 4 syringes
CAD design tubing mounts + heat gun mount and print them, along with final assembly